The finishing and the painting of the outer and inner walls of the building is completed. The tiles were laid in the girls and boys bathrooms. The windows and doors installation is completed as well. The locksmiths are working on the bunk beds, benches and tables. Part of the municipal permits have arrived and the electricity connection is under way.